Question: A project manager on a multinational website implementation project is at a party and talks to friends who will be heavy users of this new website when the project is complete and the site is rolled out. They describe some annoying aspects of the current website. The project manager takes this feedback to the sponsor, would encourages design and scope changes. Which of the following best describes what the project manager has done?
Select One
A. Scope validation
B. Integrated change control
C. Stakeholder analysis
D. Scope Review
Ans: A, The project manager has performed stakeholder analysis by learning stakeholder requirements and making recommendations to fulfill those requirements. Scope validation is a control function related to gaining customer acceptance of deliverables. Integrated change control relates to looking for multiple impacts of changes. Scope planning creates a scope management plan