Daily PMP® Quiz - Question 10 Resource Management
by Ashok Chaturvedi - At the last progress meeting, some of the team members thought that they were going above and beyond the call of duty in delivering certain aspects of the project. The project manager agreed and thought that since these key members were carrying some extra responsibility, the project could afford some special rewards such as having dinner brought in after 6 p.m. and comp time for the extra hours expended by these employees. This type of reward is called:
Select one:
a. Fringe benefit.
b. Entitlement award.
c. Perk.
d. Team building.
The correct answer is: Perk.
This is a perk. Fringe benefits are something all employees receive. Team building is an all-team activity. Entitlement award is made up.