A project manager is informed midway through project planning that she was given inaccurate data regarding new regulations affecting the required end date of her project. She may need to make a few adjustments, but she thinks she Call still manage the project to complete it before the regulations take effect. She confirms this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?
Select one:
a. Flowchart
b. Work breakdown structure
c. Critical path method
d. Precedence diagramming
The correct answer is: Critical path method
There are only two choices related to scheduling critical path method and precedence diagmmming. Precedence diagramming is a diagramming technique that deals with the relationship between activities, not schedule flexibility. The project manager is analyzing the critical path.