Daily PMP® Quiz - Question 15 Procurement Management
by Ashok Chaturvedi - With which type of contract is the seller most concerned about project scope?
Select one:
a. Cost plus fixed fee
b. Time and material
c. Purchase order
d. Fixed-price
The correct answer is: Fixed-price
In a fixed-price contract, the seller has the cost risks and therefore wants to completely understand the procurement statement of work before bidding.