A project manager's primary responsibility is to deliver the product of the project within project constraints. Actions taken and changes made to the benefit of one constraint could negatively affect another. Which of the following best describes the major constraints on a project?
Select one:
a. Scope, schedule, cost, quality, risk, resources and customer satisfaction
b. Schedule, cost, and number of changes
c. Scope, number of resources, and cost
d. Scope, cost, and schedule
The correct answer is: Scope, schedule, cost, quality, risk, resources and customer satisfaction
Scope, schedule, cost, quality, risk, resources, and customer satisfaction is the most accurate list of constraints or competing demands that a project manager must deal with it.