Daily PMP® Quiz - Question 21 Project Management Processes
by Ashok Chaturvedi - The float of an activity is determined by:
Select one:
a. Determining lag
b. Performing a Monte Carlo analysis
c. Determining the length of the time the activity can be delayed without delaying the critical path
d. Determining the waiting time between activities
The correct answer is: Determining the length of the time the activity can be delayed without delaying the critical path
The float of an activity is the length of time the activity can be delayed without delaying the critical path.