Daily PMP® Quiz - Question 30 Integration Management
by Ashok Chaturvedi - Approved corrective actions are an input to which of the following processes?
Select one:
a. Direct and Manage Project Work
b. Validate Scope
c. Develop Project Charter
d. Develop Schedule
The correct answer is: Direct and Manage Project Work
Direct and Manage Project - work is the only correct response.